Upcoming traffic changes – Bayers Road Transit Priority Corridor project

Upcoming traffic changes – Bayers Road Transit Priority Corridor project

**** HRM Release

Upcoming traffic changes – Bayers Road Transit Priority Corridor project

22558The Halifax Regional Municipality is advising residents of an upcoming full closure of the intersection of Bayers Road and Oxford Street in support of the Bayers Road Transit Priority Corridor Phase 2 project.

The intersection will be closed to all traffic from Wednesday, Oct. 14 to approximately Wednesday, Nov. 11, 2026.

Time: 24-7

Work details: This closure is required to facilitate installation of an upgraded water transmission main beneath the intersection. This Halifax Water transmission main provides water service to the north end of the Halifax peninsula.

The work involves excavation of a trench approximately 4.5 metres (15 feet) deep and requires the full width of the intersection to be closed to ensure the safety of residents, road users and construction crews.

This work is part of the ongoing Bayers Road Transit Priority Corridor Phase 2 project, which supports the municipality's Integrated Mobility Plan and Rapid Transit Strategy, and the Moving Better goals outlined in the 2026-2030 Strategic Plan.

Traffic impact: Traffic impacts are expected throughout the duration of the project and will include the following (see attached map):

Intersection closure: The intersection of Bayers Road and Oxford Street will be closed to traffic in all directions.

Bayers Road outbound lane closure and detour route: Outbound vehicles will follow a marked detour around this section of Bayers Road, between Windsor Street and Connaught Avenue, following the same route as the existing inbound detour along Windsor Street, North Street, Chebucto Road and Connaught Avenue.

Local traffic access: Bayers Road will be open to two-way local traffic on either side of the intersection closure while this work is underway.

It is expected that beginning Nov. 12, Bayers Road between Windsor Street and Connolly Street will reopen to one-way outbound traffic. Bayers Road will remain open for inbound traffic through the Connaught Avenue intersection to Connolly Street for local residents and business access only. Full two-way traffic on Bayers Road is expected to be restored on Dec. 17, 2026.

Emergency access will be maintained at all times.

Drivers should expect delays and are asked to use alternative routes where possible.

Sidewalk impact: Sections of sidewalks and crosswalks may be temporarily closed as work progresses. Access to all properties will be maintained through marked detours.

Transit impact: Halifax Transit routes will continue to follow the existing detour routes around the project area. Visit our website for up-to-date impacts to Halifax Transit routes and bus stops.

Learn more about this project at: halifax.ca/bayersroad